Prototyping is the development of a system by means of a series of iterations to incorporate midstream changes until the system meets all the business requirements.Choose the alternative that shows the correct sequence of Prototyping Development Life Cycle.
- AAnalysis → Preliminary Investigation → Design → Construction → Cutover → Complete System Components.
- BPreliminary Investigation → Analysis → Design → Construction → Complete System Components → Cutover.
- CConstruction → Preliminary Investigation → Analysis → Design → Complete System Components → Cutover.
- DComplete System Components → Preliminary Investigation → Analysis → Design → Cutover → Construction.
- EDesign → Preliminary Investigation → Analysis → Construction → Cutover → Complete System Components.