By stating that the PMBOK is generally accepted, what generally accepted mean?
  1. AIt means that the knowledge and practices described are or should be applied uniformly on all projects.
  2. BIt means that the project management team don’t have to worry.
  3. CIt means that it is appropriate for any given project.
  4. DIt means that the knowledge and practices described are applicable to most projects most of the time.
  5. EIt means that there is no widespread consensus about their value and usefulness.
Revelar gabarito e comentário

GabaritoD — It means that the knowledge and practices described are applicable to most projects most of the time.